Polysrv finishing before Polyclt

From: Nathan Acuff (nacuff@ocdnet.com)
Date: Tue Jul 18 2000 - 08:42:27 MDT


Hello all,
We seem to be having a problem with the poly-server finishing polymix-3 before the poly-client. The particulars of the test that first generated this error are:
1 pair of machines
200/sec peak rate
70% fill rate
It seems that the server machine went into the dec-2 phase almost 2 hours before the client, and consequently shut down while the client was still in top-2, completely voiding the test. Any ideas on what may be causing this and how to fix it? (short of just making the server stay in top2 until we explicitly shut it down)

Thanks,
Nathan D Acuff